For relatively stable situations,a net-change MRP is better suited than using regenerative MRP.

A) True
B) False

Correct Answer

verifed

verified

Given an order cost of $100,a,per period holding cost of $.50,and the following requirements schedule: Given an order cost of $100,a,per period holding cost of $.50,and the following requirements schedule:   What is the lot size for the second order using the part-period method? A) 80 B) 150 C) 170 D) 250 E) 230 What is the lot size for the second order using the part-period method?


A) 80
B) 150
C) 170
D) 250
E) 230

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Given the following information,develop a material requirements plan that will yield 400 units of product P at the start of week 7. 11eab92b_c482_0992_99e6_c1c02018d3a4

Correct Answer

verifed

verified

Use the fo...

View Answer

Configuring the ERP software involves reengineering established business processes to align with the ERP's procedural settings.

A) True
B) False

Correct Answer

verifed

verified

Given an order cost of $100,a,per period holding cost of $.50,and the following requirements schedule: Given an order cost of $100,a,per period holding cost of $.50,and the following requirements schedule:   What is the part-period method lot size for the order for the first period? A) 120 B) 200 C) 280 D) 350 E) 450 What is the part-period method lot size for the order for the first period?


A) 120
B) 200
C) 280
D) 350
E) 450

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

A regenerative MRP is one that is updated continuously.

A) True
B) False

Correct Answer

verifed

verified

In MRP,under lot-for-lot ordering,the size of "planned-order receipts" are equal to:


A) "scheduled receipts."
B) "planned-order releases."
C) open orders already scheduled to be delivered.
D) "gross requirements."
E) the EOQ quantity

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

A phantom bill is a special type of bill of material that is a combination of the bill of materials for a number of subassemblies.

A) True
B) False

Correct Answer

verifed

verified

Which of the following most closely describes dependent demand?


A) Demand generated by suppliers.
B) Sales forecasts.
C) Derived demand.
D) Demands placed on suppliers by their customers.
E) Net material requirements.

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

The part-period method for lot sizing attempts to balance setup and holding costs.

A) True
B) False

Correct Answer

verifed

verified

True

Great Product,Ltd.has just received an order for 100 Whozats,which must be ready for delivery at the start of week six.An MRP planner has prepared the following table showing product structure,lead times (orders are lot-for-lot) ,and quantities on hand: Great Product,Ltd.has just received an order for 100 Whozats,which must be ready for delivery at the start of week six.An MRP planner has prepared the following table showing product structure,lead times (orders are lot-for-lot) ,and quantities on hand:   How many Wherezats should be ordered? A) 400 B) 450 C) 500 D) 550 E) 600 How many Wherezats should be ordered?


A) 400
B) 450
C) 500
D) 550
E) 600

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Which one of the following is not an input in an MRP system?


A) Planned-order releases
B) Bill of materials
C) Master production schedules
D) Inventory on-hand,open orders and lead times

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

The bill of material contains information on lead times.

A) True
B) False

Correct Answer

verifed

verified

The MRP requires a list of the individual parts that will be converted to finished goods.

A) True
B) False

Correct Answer

verifed

verified

True

Ignoring the possibility of safety stock requirements,which one of the following most closely describes the calculation of net requirements for an item in MRP?


A) Gross requirements - projected on-hand - scheduled receipts
B) Gross requirements - scheduled receipts
C) Gross requirements - order releases + amount on-hand
D) Gross requirements - planned order releases
E) Gross requirements - projected on-hand + planned order releases

F) D) and E)
G) C) and D)

Correct Answer

verifed

verified

ERP automates the tasks involved in performing a business process,such as order fulfilment and financial reporting.

A) True
B) False

Correct Answer

verifed

verified

The MRP input stating which end items are to be produced,when they are needed,and what quantities are needed,is the:


A) master production schedule.
B) bill-of-materials.
C) inventory-records.
D) assembly-time chart.
E) net-requirements chart.

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

ERP involves software that is used to manage and coordinate all the resources,information,and functions of an organization from a shared database.

A) True
B) False

Correct Answer

verifed

verified

Load reports show capacity requirements for departments or work centres.

A) True
B) False

Correct Answer

verifed

verified

True

An assembly-time chart indicates gross and net requirements.

A) True
B) False

Correct Answer