Which one of the following is not common to product layouts?


A) A high rate of output
B) Specialization of labour
C) Low unit costs
D) Ability to adjust to changes in the product mix demand
E) High equipment costs

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

What is the percentage idle time for an assembly line that has 5 workstations,total idle time of 60 seconds and a cycle time of 30 seconds?


A) 10%
B) 33%
C) 40%
D) 50%
E) 60%

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

This function determines the structure of a process-that is,the sequence of operations (the workflow) ,resources,and controls needed for a particular process.


A) Structure design
B) Conceptual design
C) Process design
D) Work cell design
E) Automation

F) B) and E)
G) A) and D)

Correct Answer

verifed

verified

In which type of processing system would sugar refining be done?


A) Job Shop
B) Batch
C) Assembly
D) Continuous
E) Repetitive

F) C) and E)
G) None of the above

Correct Answer

verifed

verified

A company needs to locate three departments (X,Y,and Z) in the three areas (I,II,and III) of a new facility.They want to minimize interdepartmental transportation costs,which are expected to be $.50 per load per metre moved.An analyst has prepared the following distances and flow matrices: A company needs to locate three departments (X,Y,and Z) in the three areas (I,II,and III) of a new facility.They want to minimize interdepartmental transportation costs,which are expected to be $.50 per load per metre moved.An analyst has prepared the following distances and flow matrices:   How many least costly process layouts are there? A) 1 B) 2 C) 3 D) 4 E) 5 How many least costly process layouts are there?


A) 1
B) 2
C) 3
D) 4
E) 5

F) C) and E)
G) A) and E)

Correct Answer

verifed

verified

Using the method developed by Richard Muther,which closeness rating reflects the undesirability of having two departments located near each other?


A) A
B) E
C) R
D) U
E) X

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

Which one of the following is a type of product layout?


A) Assembly line
B) Job shop
C) Batch process
D) Functional layout
E) Retail layout

F) None of the above
G) B) and D)

Correct Answer

verifed

verified

Service process design differs from manufacturing in that it outlines the flow of the customer or something belonging to the customer.

A) True
B) False

Correct Answer

verifed

verified

The incremental approach to process design does not involve which of the following?


A) Identifying process boundaries (inputs and outputs) and the level of detail required.
B) Following the normal flow of materials through the transformation process.
C) Identifying the required activities and resources.
D) Identifying the sequence of activities and resources.
E) Determine how complete the input materials should be.

F) None of the above
G) A) and C)

Correct Answer

verifed

verified

The maker of the world-famous Widget needs to design a product layout for a new product,the amazing "Thatsit".The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 units per day.The following table describes the tasks involved in the production of a "Thatsit". The maker of the world-famous Widget needs to design a product layout for a new product,the amazing  Thatsit .The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 units per day.The following table describes the tasks involved in the production of a  Thatsit .   For output to equal projected demand,what will be the last task performed at the second workstation of the production line which uses the minimum number of workstations? A) U B) V C) W D) X E) Y For output to equal projected demand,what will be the last task performed at the second workstation of the production line which uses the minimum number of workstations?


A) U
B) V
C) W
D) X
E) Y

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Methods used to analyze data for conversion to group technology include all of the following EXCEPT:


A) statistical process analysis.
B) visual inspection.
C) examination of design data.
D) production flow sequence and routing analysis.
E) examination of production data.

F) C) and D)
G) None of the above

Correct Answer

verifed

verified

Which term is most closely associated with group technology?


A) Numerical control
B) Robots
C) Manufacturing characteristics
D) CIM
E) IDEF

F) B) and D)
G) A) and C)

Correct Answer

verifed

verified

A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day.The tasks necessary to produce this product: A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day.The tasks necessary to produce this product:   If the company desires that output rate equal demand,what is the last task performed in the first workstation in the balance which uses the minimum number of workstations? A) u B) v C) w D) x E) y If the company desires that output rate equal demand,what is the last task performed in the first workstation in the balance which uses the minimum number of workstations?


A) u
B) v
C) w
D) x
E) y

F) None of the above
G) All of the above

Correct Answer

verifed

verified

Some of the benefits of cellular layouts are less material handling and reduced setup time.

A) True
B) False

Correct Answer

verifed

verified

When higher quantities of more standardized goods or services are needed and each unit follows the same production sequence a ______ process is used.


A) continuous
B) batch
C) Job shop
D) repetitive
E) cellular

F) C) and D)
G) None of the above

Correct Answer

verifed

verified

Production process design is not part of the product design methodology.

A) True
B) False

Correct Answer

verifed

verified

Cycle time is the maximum time allowed at each workstation to complete its assigned tasks on each unit of production before it moves on.

A) True
B) False

Correct Answer

verifed

verified

Repetitive production processes produce a high volume of standardized products or services.

A) True
B) False

Correct Answer

verifed

verified

A consultant needs to locate four departments-waiting room (W) ,checkup room (c) ,laboratory (L) ,and exercise room (E) -in four areas (I,II,III,IV) of a new facility.He wants to minimize interdepartmental transportation costs associated with the nurses escorting patients,which he expects to be $.10 per patient per metre.He has prepared the following distance and flow matrices: A consultant needs to locate four departments-waiting room (W) ,checkup room (c) ,laboratory (L) ,and exercise room (E) -in four areas (I,II,III,IV) of a new facility.He wants to minimize interdepartmental transportation costs associated with the nurses escorting patients,which he expects to be $.10 per patient per metre.He has prepared the following distance and flow matrices:   What is the total flow (patients per week) between department W and department L? A) 70 B) 80 C) 88 D) 130 E) 148 What is the total flow (patients per week) between department W and department L?


A) 70
B) 80
C) 88
D) 130
E) 148

F) D) and E)
G) A) and C)

Correct Answer

verifed

verified

A company needs to rebalance a product layout for producing a redesigned product.They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day.The following table describes the tasks involved in the production of this product: A company needs to rebalance a product layout for producing a redesigned product.They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day.The following table describes the tasks involved in the production of this product:   For output to equal projected demand,what should be the actual cycle time for this assembly line? A) 0 seconds B) 3 seconds C) 9 seconds D) 10 seconds E) 28 seconds For output to equal projected demand,what should be the actual cycle time for this assembly line?


A) 0 seconds
B) 3 seconds
C) 9 seconds
D) 10 seconds
E) 28 seconds

F) None of the above
G) B) and C)

Correct Answer

verifed

verified

Showing 41 - 60 of 169