Filters
Question type

Study Flashcards

Which of the following costs is not included on a job-order cost sheet?


A) direct material costs
B) applied plantwide overhead costs
C) direct labor costs
D) actual plantwide overhead costs

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

The key feature of job-order costing is that the cost of one job differs from that of another job and must be kept track of separately.

A) True
B) False

Correct Answer

verifed

verified

When materials are requested for production the cost is removed from ____________ and added to ____________.

Correct Answer

verifed

verified

raw materi...

View Answer

Figure 5-13. During February, Alexander, Inc., worked on two jobs with the following data: Figure 5-13. During February, Alexander, Inc., worked on two jobs with the following data:    Overhead is assigned on the basis of direct labor hours at a rate of $12. During February, Job 12 was completed and transferred to finished goods. Job 13 is the only unfinished job at the end of the month. -Refer to Figure 5-13.   Overhead is assigned on the basis of direct labor hours at a rate of $12. During February, Job 12 was completed and transferred to finished goods. Job 13 is the only unfinished job at the end of the month. -Refer to Figure 5-13. Figure 5-13. During February, Alexander, Inc., worked on two jobs with the following data:    Overhead is assigned on the basis of direct labor hours at a rate of $12. During February, Job 12 was completed and transferred to finished goods. Job 13 is the only unfinished job at the end of the month. -Refer to Figure 5-13.

Correct Answer

verifed

verified

Figure 5-11. Olson Corporation constructs new homes. Assume that Olson uses a job costing system. During May of the current year, the following transactions occurred: Olson purchased $4,500 of lumber on account. Olson used $3,750 of lumber in production and incurred 50 hours of direct labor hours at $15 per hour. Depreciation of $1,500 on equipment used to build new houses was recorded. A house that was completed last period at a cost of $150,000 was sold for $180,000 in cash. -Refer to Figure 5-11. The journal entry to record the requisition of lumber for Olson would include a


A) debit to Work-in-Process of $4,500.
B) debit to Materials Inventory of $3,750.
C) credit to Finished Goods of $3,750.
D) debit to Work-in-Process of $3,750.

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Figure 5-4. Hill Company uses job-order costing. At the end of the month, the following data was gathered: Figure 5-4. Hill Company uses job-order costing. At the end of the month, the following data was gathered:    Hill's selling price is cost plus 50% for each of its products. -Refer to Figure 5-4. What is the total in Finished Goods? A)  $1,721 B)  $2,230 C)  $1,700 D)  $1,860 E)  $2,163 Hill's selling price is cost plus 50% for each of its products. -Refer to Figure 5-4. What is the total in Finished Goods?


A) $1,721
B) $2,230
C) $1,700
D) $1,860
E) $2,163

F) A) and C)
G) B) and D)

Correct Answer

verifed

verified

The difference between actual overhead and applied overhead is called an overhead variance.

A) True
B) False

Correct Answer

verifed

verified

Figure 5-4. Hill Company uses job-order costing. At the end of the month, the following data was gathered: Figure 5-4. Hill Company uses job-order costing. At the end of the month, the following data was gathered:    Hill's selling price is cost plus 50% for each of its products. -Refer to Figure 5-4. What is Cost of Goods Sold for the month? A)  $1,760 B)  $1,181 C)  $1,733 D)  $1,353 E)  $2,440 Hill's selling price is cost plus 50% for each of its products. -Refer to Figure 5-4. What is Cost of Goods Sold for the month?


A) $1,760
B) $1,181
C) $1,733
D) $1,353
E) $2,440

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Figure 5-7. Laudermilk produces dairy equipment. Most of its jobs have a number of units per job. The company has two different departments through which all jobs pass. Overhead is applied using a plantwide rate of $13 per direct labor hour. Direct labor wages average $8 an hour. Data for Job #3 for the year is: Figure 5-7. Laudermilk produces dairy equipment. Most of its jobs have a number of units per job. The company has two different departments through which all jobs pass. Overhead is applied using a plantwide rate of $13 per direct labor hour. Direct labor wages average $8 an hour. Data for Job #3 for the year is:    -Refer to Figure 5-7. Compute the cost per unit. A)  $11.58 B)  $5.60 C)  $5.73 D)  $11.45 E)  none of these -Refer to Figure 5-7. Compute the cost per unit.


A) $11.58
B) $5.60
C) $5.73
D) $11.45
E) none of these

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

Bryant Company designs and builds fancy dining room tables for individual customers. On July 1, there were two jobs in process: Job 391 with a beginning balance of $21,700 and Job 392 with a beginning balance of $8,790. Overhead costs are applied by using a rate of 70% of direct labor costs. Both jobs are unfinished on July 31. Data on July costs for both jobs are as follows: Bryant Company designs and builds fancy dining room tables for individual customers. On July 1, there were two jobs in process: Job 391 with a beginning balance of $21,700 and Job 392 with a beginning balance of $8,790. Overhead costs are applied by using a rate of 70% of direct labor costs. Both jobs are unfinished on July 31. Data on July costs for both jobs are as follows:   What is the total of the work-in-process account at July 31? A)  $28,000 B)  $58,490 C)  $68,080 D)  $37,590 E)  none of these What is the total of the work-in-process account at July 31?


A) $28,000
B) $58,490
C) $68,080
D) $37,590
E) none of these

F) D) and E)
G) B) and D)

Correct Answer

verifed

verified

Match each item with the correct statement below. Answers may be used more than once. a. Job-order cost sheet b. Time ticket c. Materials requisition form -This form may be used to maintain proper control over a firm's inventory of direct materials.

Correct Answer

verifed

verified

A company has two departments that all goods pass through, machining and assembly. Machining overhead is applied based on machine hours and assembly overhead is applied based on direct labor hours. Data on each department is as follows: A company has two departments that all goods pass through, machining and assembly. Machining overhead is applied based on machine hours and assembly overhead is applied based on direct labor hours. Data on each department is as follows:     A company has two departments that all goods pass through, machining and assembly. Machining overhead is applied based on machine hours and assembly overhead is applied based on direct labor hours. Data on each department is as follows:

Correct Answer

verifed

verified

Figure 5-8. John's Water Slides makes custom water slides for hotels. On September 1, there were three jobs in process, Jobs 812, 813, and 814. Two more jobs were started during September, Jobs 815 and 816. By September 30, Jobs 812, 814, and 816 were finished. The following data has been collected: Figure 5-8. John's Water Slides makes custom water slides for hotels. On September 1, there were three jobs in process, Jobs 812, 813, and 814. Two more jobs were started during September, Jobs 815 and 816. By September 30, Jobs 812, 814, and 816 were finished. The following data has been collected:    Overhead is applied at the rate of 120% of direct labor cost. Jobs are sold at cost plus 60%. Selling and administrative expenses for September totaled $2,950. By September 30, Jobs 812 were 816 are sold, but the customer who ordered Job 814 decided he did not want the slide so it is still in the warehouse. -Refer to Figure 5-8. What is the cost of goods sold for September? A)  $5,129 B)  $8,206.40 C)  $5,720 D)  $3,575 E)  $8,586 Overhead is applied at the rate of 120% of direct labor cost. Jobs are sold at cost plus 60%. Selling and administrative expenses for September totaled $2,950. By September 30, Jobs 812 were 816 are sold, but the customer who ordered Job 814 decided he did not want the slide so it is still in the warehouse. -Refer to Figure 5-8. What is the cost of goods sold for September?


A) $5,129
B) $8,206.40
C) $5,720
D) $3,575
E) $8,586

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Figure 5-3. Mitchell's Softball Gloves Company estimated the following at the beginning of the year: Figure 5-3. Mitchell's Softball Gloves Company estimated the following at the beginning of the year:    Mitchell uses departmental overhead rates. In the assembly department, direct labor hours are used to apply overhead. Machine hours are used to apply overhead in the testing department. Actual data for August is as follows:    -Refer to Figure 5-3. Using departmental overhead rates, which of the following is correct? A)  Applied overhead for the assembly department is $54,000. B)  Applied overhead for the testing department is $4,860. C)  Applied overhead for both departments combined is $63,720. D)  Overhead for the assembly department is underapplied. E)  None of these are correct. Mitchell uses departmental overhead rates. In the assembly department, direct labor hours are used to apply overhead. Machine hours are used to apply overhead in the testing department. Actual data for August is as follows: Figure 5-3. Mitchell's Softball Gloves Company estimated the following at the beginning of the year:    Mitchell uses departmental overhead rates. In the assembly department, direct labor hours are used to apply overhead. Machine hours are used to apply overhead in the testing department. Actual data for August is as follows:    -Refer to Figure 5-3. Using departmental overhead rates, which of the following is correct? A)  Applied overhead for the assembly department is $54,000. B)  Applied overhead for the testing department is $4,860. C)  Applied overhead for both departments combined is $63,720. D)  Overhead for the assembly department is underapplied. E)  None of these are correct. -Refer to Figure 5-3. Using departmental overhead rates, which of the following is correct?


A) Applied overhead for the assembly department is $54,000.
B) Applied overhead for the testing department is $4,860.
C) Applied overhead for both departments combined is $63,720.
D) Overhead for the assembly department is underapplied.
E) None of these are correct.

F) C) and E)
G) A) and C)

Correct Answer

verifed

verified

Which form asks for type, quantity, unit price of direct materials issued, and for the number of the job?


A) time ticket
B) materials requisition form
C) job-order cost sheet
D) None of these are correct.
E) All of these are correct.

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Consider two costing systems, normal costing and actual costing. Consider two costing systems, normal costing and actual costing.

Correct Answer

verifed

verified

Showing 181 - 196 of 196

Related Exams

Show Answer